News & Press Release -Headsup B2B enters into partnership with INA Solar
- Published onPublisher logo for "Headsup B2B enters into partnership with INA Solar"Publisher logo for "Headsup B2B enters into partnership with INA Solar"Publisher logo for "Headsup B2B enters into partnership with INA Solar"Publisher logo for "Headsup B2B enters into partnership with INA Solar"Publisher logo for "Headsup B2B enters into partnership with INA Solar"
News & Press Release -Headsup B2B Secures Mandate for 40+ MW of Solar Panels and Ancillary Products Across Rajasthan and Jharkhand
- Published onPublisher logo for "Headsup B2B Secures Mandate for 40+ MW of Solar Panels and Ancillary Products Across Rajasthan and Jharkhand"
News & Press Release -Headsup B2B Secures Rs. 16.65 Crore Debt Capital to Accelerate Growth and Innovation
- Published onPublisher logo for "Headsup B2B Secures Rs. 16.65 Crore Debt Capital to Accelerate Growth and Innovation"
News & Press Release -India’s Green Steel Push Faces Credibility Test As Emissions Rise Despite Net-Zero Pledges
- Published onPublisher logo for "India’s Green Steel Push Faces Credibility Test As Emissions Rise Despite Net-Zero Pledges"
News & Press Release -The Pulse of Progress: Industry Voices on Technological Evolution
- Published onPublisher logo for "The Pulse of Progress: Industry Voices on Technological Evolution"
News & Press Release -India’s Technology Day: From Shakti to Superintelligence—The Nation’s $1 Trillion Digital Bet
- Published onPublisher logo for "India’s Technology Day: From Shakti to Superintelligence—The Nation’s $1 Trillion Digital Bet"
News & Press Release -National Technology Day 2026: Industry Leaders Speak on Next Tech Boom and ₹1 Lakh Crore R&D Bet on Deep-Tech
- Published onPublisher logo for "National Technology Day 2026: Industry Leaders Speak on Next Tech Boom and ₹1 Lakh Crore R&D Bet on Deep-Tech"
News & Press Release -National Technology Day: Shaping India’s tech future responsibly
- Published onPublisher logo for "National Technology Day: Shaping India’s tech future responsibly"
News & Press Release -Stock Market Highlights, Sensex Today: Sensex Falls 1,312 Points, Nifty Down 360 As Oil Prices Rally
- Published onPublisher logo for "Stock Market Highlights, Sensex Today: Sensex Falls 1,312 Points, Nifty Down 360 As Oil Prices Rally"
News & Press Release -Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder
- Published onPublisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"
News & Press Release -Headsup B2B Targets INR 400 Crore Revenue Via Integrated Infrastructure Services Expansion
- Published onPublisher logo for "Headsup B2B Targets INR 400 Crore Revenue Via Integrated Infrastructure Services Expansion"
News & Press Release -What’s next in India’s EV (r)evolution?
- Published onPublisher logo for "What’s next in India’s EV (r)evolution?"
News & Press Release -Why Off-Grid Solar + Battery Storage Could Shape India’s Next Phase of Industrial Energy
- Published onPublisher logo for "Why Off-Grid Solar + Battery Storage Could Shape India’s Next Phase of Industrial Energy"
News & Press Release -Headsup B2B targets next growth phase with solar push, plans fundraise
- Published onPublisher logo for "Headsup B2B targets next growth phase with solar push, plans fundraise"
News & Press Release -Smart Energy Magazine - The Growing Importance of Technology-led Procurement and Supply Chain Platforms in Enabling Renewable Energy Projects
- Published onPublisher logo for "Smart Energy Magazine - The Growing Importance of Technology-led Procurement and Supply Chain Platforms in Enabling Renewable Energy Projects"
News & Press Release -Headsup B2B Listed as National Vendor on PM Surya Ghar Portal for Rooftop Solar
- Published onPublisher logo for "Headsup B2B Listed as National Vendor on PM Surya Ghar Portal for Rooftop Solar"Publisher logo for "Headsup B2B Listed as National Vendor on PM Surya Ghar Portal for Rooftop Solar"Publisher logo for "Headsup B2B Listed as National Vendor on PM Surya Ghar Portal for Rooftop Solar"Publisher logo for "Headsup B2B Listed as National Vendor on PM Surya Ghar Portal for Rooftop Solar"
News & Press Release -Headsup B2B enters into partnership with INA Solar
- Published onPublisher logo for "Headsup B2B enters into partnership with INA Solar"Publisher logo for "Headsup B2B enters into partnership with INA Solar"Publisher logo for "Headsup B2B enters into partnership with INA Solar"Publisher logo for "Headsup B2B enters into partnership with INA Solar"Publisher logo for "Headsup B2B enters into partnership with INA Solar"
News & Press Release -Headsup B2B Secures Mandate for 40+ MW of Solar Panels and Ancillary Products Across Rajasthan and Jharkhand
- Published onPublisher logo for "Headsup B2B Secures Mandate for 40+ MW of Solar Panels and Ancillary Products Across Rajasthan and Jharkhand"
News & Press Release -Headsup B2B Secures Rs. 16.65 Crore Debt Capital to Accelerate Growth and Innovation
- Published onPublisher logo for "Headsup B2B Secures Rs. 16.65 Crore Debt Capital to Accelerate Growth and Innovation"
News & Press Release -India’s Green Steel Push Faces Credibility Test As Emissions Rise Despite Net-Zero Pledges
- Published onPublisher logo for "India’s Green Steel Push Faces Credibility Test As Emissions Rise Despite Net-Zero Pledges"
News & Press Release -The Pulse of Progress: Industry Voices on Technological Evolution
- Published onPublisher logo for "The Pulse of Progress: Industry Voices on Technological Evolution"
News & Press Release -India’s Technology Day: From Shakti to Superintelligence—The Nation’s $1 Trillion Digital Bet
- Published onPublisher logo for "India’s Technology Day: From Shakti to Superintelligence—The Nation’s $1 Trillion Digital Bet"
News & Press Release -National Technology Day 2026: Industry Leaders Speak on Next Tech Boom and ₹1 Lakh Crore R&D Bet on Deep-Tech
- Published onPublisher logo for "National Technology Day 2026: Industry Leaders Speak on Next Tech Boom and ₹1 Lakh Crore R&D Bet on Deep-Tech"
News & Press Release -National Technology Day: Shaping India’s tech future responsibly
- Published onPublisher logo for "National Technology Day: Shaping India’s tech future responsibly"
News & Press Release -Stock Market Highlights, Sensex Today: Sensex Falls 1,312 Points, Nifty Down 360 As Oil Prices Rally
- Published onPublisher logo for "Stock Market Highlights, Sensex Today: Sensex Falls 1,312 Points, Nifty Down 360 As Oil Prices Rally"
News & Press Release -Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder
- Published onPublisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"Publisher logo for "Headsup B2B sees Rs 2,500 cr revenue by 2030: Founder"
News & Press Release -Headsup B2B Targets INR 400 Crore Revenue Via Integrated Infrastructure Services Expansion
- Published onPublisher logo for "Headsup B2B Targets INR 400 Crore Revenue Via Integrated Infrastructure Services Expansion"
News & Press Release -What’s next in India’s EV (r)evolution?
- Published onPublisher logo for "What’s next in India’s EV (r)evolution?"
News & Press Release -Why Off-Grid Solar + Battery Storage Could Shape India’s Next Phase of Industrial Energy
- Published onPublisher logo for "Why Off-Grid Solar + Battery Storage Could Shape India’s Next Phase of Industrial Energy"
News & Press Release -Headsup B2B targets next growth phase with solar push, plans fundraise
- Published onPublisher logo for "Headsup B2B targets next growth phase with solar push, plans fundraise"
News & Press Release -Smart Energy Magazine - The Growing Importance of Technology-led Procurement and Supply Chain Platforms in Enabling Renewable Energy Projects
- Published onPublisher logo for "Smart Energy Magazine - The Growing Importance of Technology-led Procurement and Supply Chain Platforms in Enabling Renewable Energy Projects"
News & Press Release -Headsup B2B Listed as National Vendor on PM Surya Ghar Portal for Rooftop Solar
- Published onPublisher logo for "Headsup B2B Listed as National Vendor on PM Surya Ghar Portal for Rooftop Solar"Publisher logo for "Headsup B2B Listed as National Vendor on PM Surya Ghar Portal for Rooftop Solar"Publisher logo for "Headsup B2B Listed as National Vendor on PM Surya Ghar Portal for Rooftop Solar"Publisher logo for "Headsup B2B Listed as National Vendor on PM Surya Ghar Portal for Rooftop Solar"

Cable Size Selection for Motors & Industrial Loads: kW to Current, Derating and Voltage Drop

7 min read
whatsapp share
x share
linkedin share
instagram share
facebook share
Cable Size Selection for Motors & Industrial Loads: kW to Current, Derating and Voltage Drop

A step-by-step method to size LT cables for motors and industrial loads — full-load current, derating, voltage drop and starting current — with a quick kW-to-amps table and a worked example.

Who this is for: Electrical contractors, plant engineers, EPC teams and procurement managers specifying LT power cables for motors and industrial loads.
I = P ÷ (√3 × V × pf × η)Full-load current formula for 3-phase motors
~2 A per kWRule-of-thumb motor current at 415 V
6–8 ×Typical starting current of a DOL-started motor vs full-load current
3–5%Voltage-drop limit commonly specified for power circuits

Source: Standard electrical engineering practice; manufacturer cable catalogues; typical project specifications, as of November 2026. Always follow the project’s design basis.

WHAT THIS GUIDE COVERS

  1. Why Cable Sizing Goes Wrong in Industrial Projects
  2. Step 1: Calculate Full-Load Current
  3. Step 2: Apply Design Margin and Derating
  4. Step 3: Check Voltage Drop
  5. Step 4: Check Starting Current and Short Circuit
  6. Quick Reference: Motor kW to Current
  7. Copper vs Aluminium and Armoured vs Unarmoured
  8. Worked Example: 37 kW Pump Motor

An undersized cable does not fail on day one. It runs hot, drops voltage, makes motors struggle to start, and slowly ages its own insulation. An oversized cable wastes money on every metre. In industrial projects with long runs, getting the size right is worth lakhs.

This guide walks through the method electrical designers use to size LT cables (up to 1.1 kV) for motors and industrial loads — in plain steps, with a worked example.

Quick answer: To size a cable for a motor or industrial load: (1) calculate full-load current, (2) add a design margin and apply derating factors for temperature, grouping and installation, (3) pick a cable whose derated rating exceeds that current from the manufacturer’s catalogue, (4) check voltage drop over the route length, and (5) confirm starting-current and short-circuit performance.

1. Why Cable Sizing Goes Wrong in Industrial Projects

  • Using the catalogue rating without derating — ratings assume standard conditions that rarely match site reality.
  • Ignoring route length — a cable that is fine at 20 m can fail the voltage-drop check at 200 m.
  • Forgetting motor starting current — direct-on-line starts pull several times full-load current.
  • Copying sizes from a previous project with different loads, ambient temperature or laying method.

2. Step 1: Calculate Full-Load Current

For a three-phase motor, full-load current (FLC) is:

Formula: I (amps) = P (watts) ÷ (√3 × V × power factor × efficiency)

Where P is the motor’s rated output, V is the line voltage (415 V in most Indian plants), and power factor and efficiency come from the motor nameplate. Always use nameplate values when available — the example values in this guide are assumptions.

3. Step 2: Apply Design Margin and Derating

Two adjustments turn FLC into the current the cable must actually carry.

Design margin

Many designers size motor feeders at about 125% of full-load current to allow for continuous duty and minor overloads. Follow your project’s design basis.

Derating factors

FACTOR WHY IT MATTERS WHERE TO FIND IT
Ambient / ground temperature Hotter surroundings reduce how much current a cable can safely carry Manufacturer derating tables
Grouping Cables laid together heat each other Manufacturer grouping factors
Laying method In air, on trays, in ducts or buried — each rates differently Manufacturer rating tables by installation type
Depth of laying Deeper buried cables dissipate heat differently Manufacturer tables for buried cables
Soil thermal resistivity Dry or rocky soil holds heat Manufacturer correction factors

Source: Manufacturer cable catalogues and standard design practice, as of November 2026.

Multiply the individual factors together. The required catalogue rating is the design current divided by the combined derating factor.

4. Step 3: Check Voltage Drop

Long cable runs lose voltage. Too much drop means motors draw more current, run hotter and may fail to start. A quick check uses the catalogue’s millivolt-per-amp-per-metre (mV/A/m) value:

Formula: Voltage drop (V) = mV/A/m × current (A) × length (m) ÷ 1,000

Compare the result with the limit in your specification — power circuits are commonly limited to about 3–5% of supply voltage. If the drop is too high, step up one cable size and recheck.

5. Step 4: Check Starting Current and Short Circuit

  • Starting current: DOL-started motors typically draw about 6–8 times FLC for a few seconds. Check the voltage dip at the motor during starting, especially on long runs. Star-delta or soft starters reduce this.
  • Short-circuit withstand: the cable must survive the prospective fault current until the protective device clears it. Check against the breaker’s clearing time and the cable’s short-circuit rating.
  • Protection coordination: the breaker or MCCB rating must protect the cable, not just the motor. See how to choose MCBs for basic coordination.

6. Quick Reference: Motor kW to Current

MOTOR RATING FULL-LOAD CURRENT (CALCULATED) WITH 125% DESIGN MARGIN
5.5 kW (~7 HP) 10.0 A 12.5 A
7.5 kW (~10 HP) 13.6 A 17.0 A
11 kW (~15 HP) 20.0 A 25.0 A
15 kW (~20 HP) 27.3 A 34.1 A
22 kW (~29 HP) 40.0 A 50.0 A
37 kW (~50 HP) 67.3 A 84.1 A
55 kW (~74 HP) 100.0 A 125.0 A
75 kW (~101 HP) 136.4 A 170.5 A

Source: Headsup B2B calculation at 415 V, 3-phase, assuming power factor 0.85 and efficiency 90%. Illustrative only — use motor nameplate values for actual design.

Use this table to estimate current — then select the cable from your chosen manufacturer’s derated rating table, not from a generic chart.

7. Copper vs Aluminium and Armoured vs Unarmoured

CHOICE WHEN IT FITS TRADE-OFF
Copper conductor Short to medium runs, space-constrained trays, motor terminations Higher material cost, smaller size for same current
Aluminium conductor Long feeders and large sizes where cost matters Larger size for the same current; needs proper lugs and jointing
Armoured cable Buried, outdoor or mechanically exposed routes Heavier and costlier, but protected
Unarmoured cable Indoor trays, conduits and protected routes Lighter, cheaper, less mechanical protection

Source: Standard industry practice, as of November 2026.

More detail: armoured vs non-armoured cable and HT vs LT cables.

8. Worked Example: 37 kW Pump Motor

ILLUSTRATIVE MODEL (HYPOTHETICAL) — 37 KW MOTOR, 150 M CABLE RUN

Supply415 V, 3-phase
Assumed power factor / efficiency0.85 / 90%
Full-load current67.3 A
Design current (125%)84.1 A
Combined derating factor (assumed)0.80
Required catalogue rating105.1 A or more
Voltage drop with assumed 1.1 mV/A/m11.1 V (2.7% of 415 V)
ResultCandidate size passes a 3–5% voltage-drop check

Hypothetical example with assumed values, for illustration only. Actual sizing must use motor nameplate data, the selected manufacturer’s rating and mV/A/m tables, and the project’s design basis — verified by a qualified electrical engineer.

⚠ COMMON MISTAKES
  • Picking a size from the catalogue without applying derating factors.
  • Skipping the voltage-drop check on long runs.
  • Sizing for running current but ignoring DOL starting current.
  • Using generic charts instead of the selected manufacturer’s tables.
  • Protecting the motor but not the cable with the breaker rating.

KEY TAKEAWAYS

  1. Start with full-load current from the motor nameplate.
  2. Apply a design margin and every relevant derating factor.
  3. Choose from the selected manufacturer’s derated rating table.
  4. Check voltage drop on every long run.
  5. Account for starting current and short-circuit withstand.
  6. Get final sizes verified by a qualified electrical engineer.

Choosing a cable brand? See top cable companies in India.

Need LT Power Cables for Your Project?

✓ Copper & aluminium, armoured & unarmoured ✓ Verified suppliers across top brands ✓ Pan-India delivery

Get a Quote

Disclaimer: This guide explains general cable-sizing methodology for information only. Values in examples are assumptions. Cable sizing for any installation must be carried out by a qualified electrical engineer using motor nameplate data, manufacturer rating tables and applicable standards and codes.

Frequently Asked Questions